The school has approved up to RM88 million for the wider project, which includes a RM60.38 million building contract.

The International School of Kuala Lumpur (ISKL) says work is getting under way this month on a campus upgrade in Ampang Hilir. The school’s master plan sets out changes to classrooms, performance spaces and sports facilities, with work expected to span about two years.

Space Alliance Contracts accepted a RM60.38 million building contract on 19 November, according to its parent company, Signature Alliance Group. The school’s separate budget of up to RM88 million covers the wider project and the cost of preparing the new facilities for use.

New Labs, a Theatre and a Shaded Plaza

The school plans to replace its open-air amphitheatre with Rimbun Plaza, a shaded space for outdoor learning, performances and gatherings.

Nearby, a three-storey building called the Bright Box will house labs for design technology, computer science and robotics, and film and media. A flexible studio theatre will seat 150 to 200 people.

The master plan also includes improvements to four tennis courts and a new indoor golf centre. \

The Edge Malaysia, citing the contractor’s filing, reported that the covered-court works carry a six-month completion period from their own start date.

How the School Plans to Keep Classes Running

ISKL says it has already moved affected learning spaces and will secure construction areas separately from pupil spaces. It says families will receive updates if drop-off, pick-up or pedestrian routes need to change as work progresses.

The building contract sets an 18-month period from the start of its first phase. Each contract phase has its own start date, to be communicated by the architect. The school’s roughly two-year estimate covers the broader campus project.

The school’s project page carries its plans, renderings and information for current families.